How Long Does It Take to Build a Custom Home?
Your timeline depends on three things more than anything else: how ready your plans and selections are, your building site, and the Michigan weather.
The Timeline, Stage by Stage
| Stage | Typical time |
|---|---|
| 1. Design and plans Your plan drawn or changed in CAD | 2 – 3 weeks |
| 2. Estimate and financing Final price, construction loan approval | 20 – 30 days |
| 3. Permits Most can be applied for at the same time | 2 – 3 weeks |
| 4. Site work and foundation Excavation, footings, basement walls, backfill | 3 – 5 weeks |
| 5. Framing and roof | 3 – 6 weeks |
| 6. Windows, doors and rough-ins Plumbing, electrical, heating, plus inspections | 3 – 5 weeks |
| 7. Insulation and drywall | 3 – 4 weeks |
| 8. Interior finishes Trim, cabinets, countertops, flooring, paint | 6 – 10 weeks |
| 9. Final work Driveway, grading, final inspections, occupancy permit | 2 – 4 weeks |
Stages overlap on most jobs, so the total is usually shorter than adding up every line.
Permits and Approvals You May Need
A new home needs more permits than most people expect. They usually take 2 – 3 weeks, and many can be applied for at the same time.
- Address assigned for the new home
- Driveway permit
- Well permit, or city water approval
- Septic permit, or sewer approval
- Soil erosion permit, sometimes, depending on how close the site is to water or a wetland
- Zoning and building permits
- Electric and gas service applications, overhead or underground
Electrical, plumbing and heating permits are pulled by each licensed subcontractor.
That's a lot of paperwork for one house. We handle it for you as part of building your custom home.
What Slows a Build Down
- Late selections. Waiting to choose cabinets, flooring or fixtures can stall the finish stage for weeks.
- Changes after construction starts. Moving a wall is easy in CAD and costly once it's framed.
- The building site. Wet soils, a hard-to-reach water supply or extra tree removal all add time.
- Michigan winter. Concrete driveways, final grading and landscaping often wait until spring.
- Financing. Each construction loan draw needs an inspection, and slow draws can hold up subcontractors.
How to Keep Your Build on Schedule
- Finish your plans before you start. We design in CAD so you can see the home and make changes on screen, not on site.
- Make your selections early. Pick cabinets, counters, flooring and fixtures before framing is done.
- Get your financing lined up. Talk to your lender about a construction loan as soon as you have an estimate.
- Have your lot checked first. Soil, water, septic and access questions are cheaper to answer before you buy.
When Is the Best Time to Start?
Plan over the winter and break ground in spring. That gives you the full building season for the foundation and framing, and gets the house closed in before the next winter.
Winter starts are possible too. During a mid-winter break in the weather, we can dig the basement and pour the foundation. The concrete is mixed with hot water and cold-weather additives, and the poured wall crew covers the walls with blankets when needed. Outside work like driveways and landscaping still waits for spring.
Get Your Timeline and Your Price
Every home and every lot is different. Start with a free estimate, then call David to talk through your plans and schedule.